The pressure housings have been moving back and forth between the lab and the machine shop again this week so I’ve gotten more of a workout. Once they’re finally all back I’ll be able to start verifying them. The verification is to ensure that the parts have been machined in accordance to the drawings. The machine shop also finished with the vacuum ports so I can fit check those once the end caps come back.

I’ve started working on taking inventory of all the wire. It’s certainly taking longer than I thought it would since what is written on one document may be different than what is written on another document which both may be different from what is actually labeled on the wire. Once it’s all sorted out though there will be a nice wire list. Some of the wires are being replaced so we need a list of what kind of wire is connected where. That way it’ll be easy to look at the list and say ‘we need to replace this type and it’s used in these locations’.

Though no longer on the sub, these are some of the wires I am taking inventory of. And yes, they still look like that.