Week 11: Forklifts, A-frames, Cranes, and a Big Ol’ Engine

This was an exciting and successful week! We developed a plan to move the F.G. Walton Smith aft a few feet so that it would rest flush against the finger pier that tied up the stern, so that the A-frame would be directly above the dock and therefore would be able to lift the new engine onto the deck. This manuever had never been done before and so we needed to test if a couple things were possible first, so there was a lot of contingency planning and troubleshooting weaknesses in the plan. Some of the problems trying to lift the new engine block with the heads on were:

– The cranes onboard couldn’t lift the full 4780 lbs of the new motors with the jib fully extended. Therefore we needed to find a way to get the engines on deck and resting next to the soft patch, so that the cranes could lift with the jib knuckled in. 

– The finger pier structurally has these wooden slats that are along the middle of concrete supports, which run along the whole pier. The worry being if the big forklift with a large boom extension carrying the new motors would be too much weight for the wood slats to bear. These wood slats are comprised of 3 2x4s held together by rebar with small 2×2 spacers in between them. We found out later that they are made of Ipe, a brazilian hardwood, that is actually one of the five strongest woods in the world. However, the slats are varying degrees of age and degradation and there was still worries. 

– The A-frame boom rams when resting on the supports are completely stowed in the ram cylinder and provide an approximate 5-7 foot overhang off the stern. The centerline winch runs off the hydraulics powered by the generators and is rated for 7,000 lbs, which would make it ideal to lift the engines. The only drawback was that SWL was rated with the A-frame in the stowed position and not with the rams extended, therefore it was undefined and untested how far the A-frame could  boom in. 

So, at the beginning of the week we coordinated with the Campus Facilities personnel to put metal plates into the pier in lieu of the wooden slats. But upon later testing found that we also needed to strengthen those supporting it with the wooden slats and 6x6s as well. We moved the ship back timing it with the outgoing tide and working the lines, I learned from school this is called ‘warping’ a ship. The next step was to test the A-frame, pier, and forklift capabilities to move the engines weight. The crew had some old train wheels that in total weighed 5200 lbs lying around in the shop and those were forklifted out to the pier, brought down the finger pier and hoisted with the A-frame. The results were a success as the A-frame was capable to lifting the weight safely until at a vertical angle with the deck. It then would be possible to walk the engine from the center of the deck next to the soft patch utilizing Lock and Ron’s portable A-frame chain hoist bar. After these initial tests, we accomplished getting the brand new portside engine onto the deck and into the port engine room by Thursday afternoon. Here are some pictures of the whole process:

 

It was very exciting to conduct all of this planning and testing to find that it was a very plausible idea to get the engines onboard and moved where they needed to go and very rewarding to finally do it after all was said and done. On Friday, we put the engine mount dampeners in, moved the engine forward and blocked it up, then got back to cleaning the starboard side bilges. The starboard side engine room brings more challenges than the first, so our successes with the portside engine quickly turned into worries about doing the other engine. But that will be figured out hopefully soon as the plan is to attempt to get the other one on board next week. 

Week 6 – Syenna Graham

Hello!

This week I worked on datapods and went to a few talks giving by the MIT joint program students and scientists. I also went to the Woods Hole film festival, the movie the played was about trailerpark ownership in the US. Other than that I am still going to the beach everyday, eating seafood and going to the free aquarium to see the seals!

– Syenna

Walton Smith Week 11: Removal of the engine mounts and cleaning the bilge

This week was relatively short for me as I took 2 personal days off, Thursday and Friday. Both Monday and Tues day was spent removing the mounts the engines sat on. This was a very laborious job that took lots of leverage to complete. The bolts for the mounts were seized in place so we had to use lots of PB Blaster, a lubricating oil that eliminates rust, corrosion, and sticking, and place pipes over the end of the rachet to act as a cheater bar to increase the amount of torque. Even this at times didn’t help, a persuader had to be used (a hammer) to dislodge some of the rust and free up some area to work with. On Wednesday we spent the day cleaning out the port engine room bilge. There was so much accumulating oil from over the years that it turned into sludge. We spent hours that day using degreasers and a pressure washer to clean the bilge. By the end of the day the bilge was noticeable cleaner but not fully cleaned. Once the bilge is clean then it will be time to paint it.

Week 10: Cleaning Bilges, Mounting Wifi, Running Cable

After a busy last week getting the engines out, it has slowed down this week. We have had to pump out slop from the bilges, clean them with the pressure washer, get them all dry, and put paint in the bilges before the new, clean, red engines go in. This mostly took up the beginning of the week along with some crane ops and moving/removing various items ranging from engine room parts to tools and materials. The ship is a mess with so many projects and equipment being used. Alesha and I have many side quests from Denis to install the wifi, run the POSMV wires and set up that system, run the wires for the starboard and port side cameras, reconstruct the CTD, and make new terminations on the 3-2-2 wire. We also have side quests from Jon to finish the A/C installation in  Cabin 9, make a shelf, and insulate some more A/C piping. The main mission of course right now is figuring out how to get the new engines at around 4,500 lbs onto the ship and into the engine room cleanly and safely. Then, to repower and run controls to all of the steering stations onboard. 

In the latter part of this week, I worked on making some holes in the overheads to run RJ45 wire to the two different wifi modems. I also had to mount the modems and figure out where to put the relay boxes for easier maintenance later on. 

Week 5 – Syenna Graham

Hello!

I am in week 5 of my internship, i’m now just starting to get really comfortable with how the software processes work on the Sentry team and biking everywhere in Woods Hole!

This week I …

– Went to the Woods Hole aquarium 

– Went to Martha’s Vineyard

– Fixed a booting issue on a portable server

– Installed OS/software on a datapod (a computer that collects data on sentry while underwater) and verfied that it works well

– Learned about servo/encoder software at a Sentry engineering meeting 

– Got raging poison ivy!

 

Have a good week,

Syenna

Walton Smith Week 10: Removal of the engines

This week was remarkably busy and tiring. On Monday, the weather was not in our favor to pop open the soft patch, breaking the watertight seal, so we began stripping everything off the starboard engine: aftercooler, exhaust manifold, raw water pump, alternator, and coolant reservoir. By Tuesday, the weather was looking better so we pulled up the decking to expose the soft patch, scraped off the 5200, and pulled off the soft patch. That was the easy part of the day. Following, we hooked the engine up with the crane and attached the Dillion tension load cell between the engine and the crane wire. Upon lifting we realized the engine still weighed 4,560 lbs., over the SWL for the extension of the crane, it was now time to remove at least 1,000 lbs. We started by removing the 6 valve covers (one for each cylinder and not one large one), followed by removing the cylinder heads, valves, injectors, and rocker body. Tuesday night I got the wonderful news that I had the opportunity to extend my internship until the middle of September and gladly accepted. By Wednesday morning, the engine was ready to be lifted again to remove it from the engine room. This time, it weighed exactly 1,000 lbs. less. We were now able to lift the engine and move the crane safely. This took some time as we had to avoid the generator that was sitting close by, as well as a seawater discharge pipe that stuck out about 4 inches from the edge of the soft patch. We were able to lower the engine in the middle of the deck, where the starboard crane would pick up the engine and place it on the dock. While the engine as placed in the middle of the deck on blocks, the oil pan was reattached. By the end of the day, the engine was blocked under an overhang to protect it from rain. By Thursday, we knew exactly what we needed to remove from the starboard engine to make it light enough for the crane. We started with breaking the head bolts and removing the heads, valves, and injectors to remove all that weight from the engine. This was all followed up by decluttering the area around the engine to be able to shift it aft without anything being in the way. By the end of the day Thursday, the engine was moved aft under the soft patch and ready to be removed Friday morning. Friday morning was started by removing a light fixture that was hanging off the soft patch, removing the decking and stairwell on top, then popping off the patch. The starboard engine was far more difficult to remove from the engine room because the hydraulic fluid tank occupied half, if not more, of the working area under the patch to more the engine around. Because of that, we had to keep problem solving ways to angle and maneuver the engine to shimmy it out. Once out of the engine room and lowering onto the dock everyone was relieved and excited. As the engines weight was removed from the crane onto the dock, the boat rose about 6 inches out of the water. With both engines out and off the boat, we removed nearly 5 tons, setting us below our lowest draft mark. Having both engines out was a fantastic way to end the work week.

   

Week 9: Successfully Removing Both Engines

This past week was full of sweat, hard work, and heavy lifting. Starting on Monday we started stripping the starboard side engine’s after cooler, exhaust manifold, coolant reservoir, raw water pump, and decouple the wiring harnesses. As the weather was favorable, on Tuesday we were ready to attempt taking the portside engine out. We had several pallets full of heavy engine parts to get off the deck and the soft patch over the engine room to bring up before we could attempt lifting the engine out of the hatch. We decided to use the Dillon Load Tester on the crane to see how much the engine weighed with the heads on as it would be the most ideal situation to leave the internal parts of the preexisting and new engines unexposed. However, upon lifting the engine we discovered that lifting the engine out with the heads on would be impossible as the crane was only rated for 3,300 lbs with the jib fully extended. The engine with the heads on weighed 4,600 lbs. So, we managed to get the engine back on blocks and started breaking the heads loose. This includes taking off the head covers, taking out the rocker body, removing the injectors, and taking off the exhaust and intake valves. Here is a picture of me with the head covers off and internal valve springs exposed:

Wednesday morning we were ready to try again and get the engine block out. It weighed 3,560 lbs with the heads off and so it was a bit sketchy when the crane moved it to the center of the deck but everyone was highly vigilant and making sure everyone stayed safe. It was a success and we put the oil pan and flat plate back on while it was on deck. It was then picked up by the second crane and moved to the pier to be taken away by the forklift. Here is a picture of Alesha and I with the engine block resting on the back deck:

On Thursday, we continued stripping the starboard side engine and removing the heads as we learned our lesson from trying to lift the other one with the heads on. We then began to move the engine aft on the A-frame. This was a bit more tricky as the hydraulic pumps and tank for the cranes was in the way to get the engine out of the soft patch. It was a long day as it had taken us two days to move the other engine back in three regroups of the A-frame, while we did this engine in one day with two regroups of the A-frame. It is pretty cool working with everyone though as it is like solving a puzzle of finding the best and safest ways to clear things in our way. It seems that ideas flow and as soon as someone is off on a mission to get the right tool or another block of wood that another idea pops up that suffices. It was a very collaborative effort made fun with jokes, music, and a little edginess of lifting something so heavy around such a cramped engine room. 

By Friday morning, we were ready to lift the soft patch and hoist the engine out which was tricky as that hydraulic pump and tank if hit or pushed up against by the engine block could shut the whole crane down. That is the same crane that we were using to lift the engine up and out of the hatch. It literally took all of the crew, Alesha and I, Ron and Lock and Ron’s son, and Don Cucchiara to figure out how to get this engine out of the hatch sharing ideas and different perspectives as we all had different aspects of what was going on and concerns. We ended up getting it out after a few hours without damaging any of the hydraulics or anyone getting hurt. Here is a picture of Jon, our Chief Engineer and previous MATE intern next to the starboard side engine on blocks:

We concluded the week by also taking out the CO2 tanks to get recertified and took a long swim on the beach as we were quite dirty and sweaty. This experience has been capitalized by a great crew, wonderful working environment, and lots of in-depth experiences on a variety of maintenance projects. I am happy and grateful to be able to extend the internship until September 13th and stick around to see the end of this engine project with the F.G. Walton Smith. There are lots of great people at RSMAS that are on the forefront of trying to make the world a better place through Coral Research and Reconstruction, Underwater Archaeology, and Hurricane Research. Here is a picture of us enjoying the weekend in Wynwood with some of our RSMAS friends:

Week 4 – Syenna Graham

Hello,

This week i’m completing troubleshooting tasks to get the some of the software components ready to go back out to sea.

Such as, fixing ethernet ports on one datapod (one of the computers that collects the data for Sentry when its underwater), installing operating systems on another datapod and fixing booting issues with a server.

 

– Syenna 🙂

Walton Smith Week 9: Disassembling the engine

This week was all about getting ready to remove the engines and dissembling one. To start the week, we drained the oil out of the port engine. In the process of getting a 55 gallon barrel for the coolant to be collected in, we stopped at the machine shop to clean up some space to work and put parts for when the engines arrive. To finish the day, we removed the air intake manifold on the port engine.

Tuesday was a relatively slow day, as it took some time to drain the coolant out of both engines. The drain was in a low spot were only a 1.5 gallon bucket could fit so there was a bunch of stop and start with the flow of the coolant from the engine. We removed the air intake manifold from the starboard engine, then removed the coolant reservoir for the port engine. To finish off the day we cleaned and organized the deck. Although not much was completed, all the jobs were tedious in their own way.

The rest of the week we spent disassembling various parts of the engine to lighten the weight for the crane: oil pan, turbo, aftercooler, exhaust manifold, raw water pump, and alternator. Once we set up the A-frame and were able to lift the engine a bit, we shifted it forward to disconnect the flywheel from the torque converter. By Friday afternoon, the engine was unseated, raised, and placed on blocks directly below the soft patch, ready to be removed the following week.

Later Friday evening, the new engines showed up! Fire engine red and ready to be used. I cannot wait to see them running!

   

New diesel Cummins engines, fire engine red for more speed.

      

The process of hoisting the engine on the A-frame with 2 diesel experts.

Week 8: Deconstructing the Port Side Engine

The engine project has been started as we got the other exhaust out last friday and started pulling off parts of the portside engine this week. We first had to drain the system of coolant and oil. We then proceeded to take off the coolant reservoir, air intake, turbo, aftercooler, exhaust manifold, alternator, raw water pump, oil pan, and the pick-up tube. We had to move all that we could out of the way including the raw water piping from both the diesel generator and the main engine. The engineers that are in charge of repowering the F.G. Walton Smith are two old salty guys that have been working with Cummins, Caterpillar, Detroit, and doing these engine rebuilds for an accumulated 80+ years. Their relationship is straight out of a movie and they are fun to work with, their names are Ron Cheeseman and Lockwood. Here is a picture of me working with Ron taking apart the engine: 

By today, we have finally got the port engine decoupled and up on an A-frame attached to two 3-ton chain hoists and resting on blocks prepared to move and lift through the soft patch on the aft deck. It has been great experience taking the engine apart, looking at all of the mechanical parts and understanding how they are put together and work. It is also quite impressive to see and use the equipment required to lift these engines with such experienced guys. It puts in perspective how demanding and complex of a project this is but also how it is absolutely possible to do pretty much anything. These guys take on big jobs and get them done no matter what and have been doing it for many, many years. Here is a picture of Alesha, Ron’s son, and I with the engine on blocks:

Here are some additional pictures of the engines deconstructed and me underneath unscrewing the oil pan: